Investment Opportunity
Explore investment opportunities in Piura LNG's modular liquefaction project
Investment Overview
Piura LNG represents a strategic investment opportunity in Peru's growing energy sector, with a phased development approach that optimizes capital efficiency and market responsiveness.
Phase 1: 0.5–1.0 MTPA (FLNG)
Estimated CAPEX range: $500-800 million
Initial phase utilizing floating LNG technology to enable rapid market entry with lower upfront capital requirements.
Phase 2: 2–3 MTPA (Onshore)
Estimated CAPEX range: $1.5-2.5 billion
Expansion phase implementing modular onshore liquefaction facilities with increased capacity and efficiency.
Key Financial Indicators
- Attractive IRR projections based on regional LNG pricing
- Competitive levelized cost of LNG (LCLNG)
- Flexible commercial structure with multiple revenue streams
- Projected payback period of 7-9 years for Phase 1, 5-7 years for Phase 2
Investment Opportunities
Project Timeline
1
FEED (Front End Engineering Design)
6-9 months
Detailed engineering design, cost estimation, and project planning phase.
2
EPC (Engineering, Procurement, and Construction)
36-48 months
Construction of liquefaction facilities, storage tanks, and marine infrastructure.
3
Commissioning and Start-Up
4-6 months post-construction
Testing, validation, and initial operation of the LNG facility.
4
Commercial Operation Date (COD)
Targeted for the fourth quarter
Full commercial operations begin, with LNG production and export activities.